Case study 053 · Loving County, Texas
A biomineralization treatment eliminated annular gas and fluid flow after multiple conventional cement-squeeze attempts were unable to establish injection.
The challenge
The vertical Cherry Canyon producer was drilled and completed in 2005. The surface casing crossed a salt zone with little or no cement coverage across the shoe, leaving an annular pathway for gas and fluid migration.
Multiple conventional squeeze attempts were made across two depth intervals, but the operator could not achieve injection. The well was re-perforated at 854–857 feet to provide access for a targeted biomineralization treatment.
The treatment
A retrievable bridge plug and packer isolated the treatment interval.
With the surface casing vent open, staged treatment addressed the connected upward pathway.
With the vent closed, the response showed an immediate injection-rate reduction of more than 80%.
MacroSeal™, MicroSeal™ and NanoSeal™ were applied to progressively close the accessible defect sizes.
The result
Persistent annular flow eliminated where conventional squeezing could not gain access.
The treatment demonstrates how water-like delivery and staged mineralization can reach a connected pathway and build a permanent barrier in place.
Persistent leaks can turn a routine plugging schedule into repeated remedial work. Planning those wells into a dedicated treatment sequence gives operators more control over access, verification, and the work that follows.