Isolate
The existing bridge plug and cement were used to isolate the target below the leaking interval.
Case study 058 · La Plata County, Colorado
A rigless BioSqueeze treatment sealed casing leakage at approximately 7,800 feet, preserved internal diameter and restored mechanical integrity.
The challenge
An operator contracted BioSqueeze to restore mechanical integrity on a disposal well in the San Juan Basin. Diagnostics isolated leakage to a 32-foot interval on the 4½-inch production casing at approximately 7,800 feet.
Two conventional cement squeezes had been attempted with low confidence in placement and no meaningful improvement in pressure-falloff performance.
The treatment
The existing bridge plug and cement were used to isolate the target below the leaking interval.
A packer was set at 7,774 feet and a capillary string placed through it to 7,825 feet.
The workover unit moved to another well before BioSqueeze began the treatment.
Injection pressure was raised in steps, sealing accessible pathways at each pressure level before moving higher.
The result
Leaks sealed. Internal diameter preserved. Injection resumed.
The methodical pressure-stepping strategy allowed mineral formation across accessible defects ranging from sub-micron gaps to larger connected channels.